Project Role:
Teleo Engineering developed and managed the installation of 2 x x x sized pumps, vacuum pumps and assemblies, process equipment, structural buildings, crane, water separators for the pumps, water circulation tank design and installation.
Teleo Engineering specified, procured and installed a detonation flame arrestor, complete with bypass valves to allow for cleaning.
Teleo Engineering developed, installed and commissioned PLC Control software that was installed into the mine fibre background and required upgrades to the power supply and electrical reticulation.
Teleo Engineering successfully delivered the project that increased the gas extraction from underground, which reduced the risk of outages due to high methane levels.
Project Assignment:
To provide a project development and management for the upgrade of a brownfields gas vacuum plant, which included defining the project, the proposal for budget approval, managing the design procurement and the installation of the project.
Associated Services:
- Project Development
- Project Delivery